ASAT, the water and sewerage authority of Antalya, held a tender on 7 October to expand the wastewater treatment plant in Mahmutlar. The same package covers new pre-treatment equipment at the plant in Gazipaşa. The works are valued at 457.5 million Turkish lira. The lowest price, 390.98 million lira, came from a joint bid by ACD Mühendislik and Uygur Yapı. The bids are still being checked, and no contract has been signed yet.

The Mahmutlar plant is designed for 20,000 cubic metres of wastewater a day. In the project documents ASAT explains why it needs rebuilding: the district now has more permanent residents and more tourists, the equipment is worn out, and the plant gives off a smell. The two existing aeration tanks will be fitted with membrane units for 25,000 cubic metres a day, and the plant will also get two ultraviolet disinfection units, three decanters for dewatering sludge and five blowers. Under the tender terms, construction is allowed 240 days from the day the site is handed over to the contractor.

Home buyers usually look at the sea, the shops and the roads, and only think about the sewers when something goes wrong in summer. Yet every new building in Mahmutlar, whether a finished project or one of the residential complexes under construction, is connected to the same plant. A developer in Turkey builds the house and the pipes leading to it, while the amount of wastewater the plant can take is ASAT’s responsibility. If you are choosing a flat from the catalogue, it is worth asking how the building is connected to the mains, just as you would ask how far it is to the beach.

Frequently Asked Questions

When will the expansion of the Mahmutlar treatment plant be finished?
Under the tender terms the works are allowed 240 calendar days after the site is handed over to the contractor. As of 14 October 2026 no contract has been signed, so there is no exact completion date.
Who is responsible for sewerage and treatment plants in Alanya?
Water supply, sewerage and treatment plants in Alanya, as in the rest of Antalya province, are run by ASAT, the water and sewerage authority of Antalya Metropolitan Municipality.
How much does the expansion of the Mahmutlar treatment plant cost?
The estimated cost, together with the new pre-treatment equipment in Gazipaşa, is 457.5 million lira. The lowest bid at the tender was 390.98 million lira.